Lakeside Views
13.71-hectare residential area with 500m of frontage along Concession Road 5 and 315m of frontage along Osborne Street. The subdivision will contain 144 single-detached, 54 semi-detached, 6 street townhouses, and 24-48 live-work townhouses.
Location Map
Site Map
Signage Map - As blasting moves closer to the road (30m) expect traffic stoppage and delays as indicated by the stop and slow signs on this map.
Project Update
- August 3, 2022
- Blasting on site for all internal sewer infrastructure is complete. Note: Blasting may be used for the installation of the proposed external sewer infrastructure dependent on the in-situ rock levels and proximity to existing infrastructure.
- Servicing infrastructure within the development will commence early to mid August once adequate water is pumped offsite. Sewer infrastructure will begin at the low end (Lakeside Loop & Conc 5) and work up towards Bedrock Lane & Osbourne Street.
- Servicing infrastructure offsite along Concession 5 and Durham 23, will commence once final approval from Durham Region is in place.
- Water pumping within the development is essential to install the servicing infrastructure, as the water table is relatively high, and located just below the shale. Water pumping will follow existing external drainage paths and upon final approval by Durham Region, the drainage of storm sewers will outlet along Concession 5, north of Durham 23.
- Shale rock stockpiled on site will be crushed and tested by Geotech for use as granular and/or fill onsite.
- Construction phasing : Fill importing will continue and be ongoing from pre-approved sites, base asphalt on interior roads is expected in approximately 6 months.
- April 28, 2022
- Tentative Blasting Schedule:
- Monday May 2, 2022: Monitoring and Set Up
- Wednesday May 4, 2022: Surveying
- Thursday May 5th and Friday May 6th, 2022: Blaster Mobilization
- Monday May 9, 2022: Commence Blasting
- Six (6) to Eight (8) weeks
- February 10, 2022
- The Haul Route will cover 42.6 kilometers and will affect the following roads in Brock Township:
- Highway 12 North
- Highway 48 East
- Regional Road 23 (Osborne Street) North
- 5th Concession - Thorah - East
- February 9, 2022
- Please be advised that fill importation will begin on February 10, 2022, with an expected 50 - 60 loads being brought in per day.
- January 29, 2022:
-
Please be advised that the developer of the Beaverton Lakeside Views subdivision, located at Concession Road 5 and Osborne Street in Beaverton, is currently utilizing heavy equipment to break through the rock in order to reach an appropriate depth to install the municipal services that are required for this project. This work is required for the project to move forward and will be completed as efficiently as possible. We appreciate your patience through the increased noise and disturbance created by this construction work.
- August 23, 2021:
- Blasting operations - Blasting of pond to be completed mid-December 2021, blasting for sewers to commence in 2022.
- November 16, 2021:
- Future Labour:
- Servicing will start in end of Jan/early Feb 2022 (Based on the current working conditions)
- Construction will start mid-July 2022.
- First tentative closing will be in March/April 2023.
Working Hours:
7:00am - 7:00pm weekdays
Contact:
Best Developments - (905) 479-9600 or paula@besthomescanada.com
Blasting contact: ROCK BREAKERS 2007 Inc. – 705-789-5666
|
Beaverton Common
6,650 square metres of commercial space, retirement living, and adult lifestyle residences.
Location Map
Project Update
- September 11, 2021:
- December 13, 2021:
- Grading operations of commercial area:
- Preparation of the fill areas (1-2 days);
- Excavation and relocation of material onsite to the fill areas (3-4 days); and
- Restoration of the disturbed areas (1 day)
- Future Labour:
Working Hours:
8:00am - 5:30pm weekdays
Contact:
Frank Mazzotta, Armour Heights Developments - (905) 303-7800 or info@armourhd.com
|
Location Map for Logan Homes
Vegetation Removal
The works will involve the cutting and chipping of trees and shrub/brush in advance of the bird breeding season within limits of the Draft Plan of Subdivision S-B-2017-01. A Tree Inventory and Preservation Plan (TIPP) was approved as part of the Draft Plan of Subdivision application. The attached Figure 3 from the TIPP shows the trees and tree groups to be removed, and all shrub/brush vegetation within the red line (Subject Property) will be cut and chipped. Through the approval of the Draft Plan of Subdivision S-B-2017-01, the owner has agreed to provide compensation in accordance with the Lake Simcoe Region Conservation Authority Ecological Offsetting Policy. The on-site vegetation removal work will be completed by March 31, 2022
|